Deploy Origen Quad-Core Boards in Lab
We have some new Origen Quad-Core boards we need to deploy in the lab. The dev-platform team is churning out hwpack+rfs for it during 2012.12. We should build a master-image from their output, deploy our boards to the farm, and set up and image-reports view in LAVA for this once the daily CI job is in place.
Blueprint information
- Status:
- Complete
- Approver:
- Alan Bennett
- Priority:
- High
- Drafter:
- Tyler Baker
- Direction:
- Approved
- Assignee:
- Dave Pigott
- Definition:
- Approved
- Series goal:
- Accepted for trunk
- Implementation:
- Implemented
- Milestone target:
- 2013.04
- Started by
- Dave Pigott
- Completed by
- Fathi Boudra
Related branches
Related bugs
Sprints
Whiteboard
Meta:
Headline: TBD
Acceptance: TBD
Roadmap Id: CARD-253
[asac, Feb 2, 2013]: origen quad has to take a back seat this month as dave is struggling with an increasing amount of high priority tasks. medium priority make sense. Just means that it's unlikely to land for february release; this will go through post mortem and milestone will be bumped to march there. Please raise your hand if customers expected this to land in LAVA this month (wrt member build).
[danilo, March 27, 2013] Moving to next month as per postmortem.
[dpigott, April 3, 2013] No Ubuntu available for master - consulting with Anmar
[dpigott, April 3, 2013] Anmar says there is no need for them in the lab so this will never be completed
[2013-04-24 asac] Headline/acceptance missing. please follow points I mentioned before when drafting these. Since fathi already scraped stuff from here, update here and also on his highlights page (like with every headline for this month)
Work Items
Work items:
Build up stacks: DONE
Get shelves drilled: DONE
Order any extra parts required: DONE
Deploy in lab: DONE
Create Master Image: POSTPONED
Run first boot: POSTPONED
Run health check: POSTPONED
Dependency tree
* Blueprints in grey have been implemented.