Quarterly Progress bar/metric for Lane view
A progress bar at the top of the lane view, counting blueprints completed vs. planned rolled up for all cards.
This is needed to replace our currently used Metric "% Requirements Complete" with something meaningful for our new monthly/quarterly engineering cycle. See: https:/
Blueprint information
- Status:
- Complete
- Approver:
- Данило Шеган
- Priority:
- High
- Drafter:
- Mattias Backman
- Direction:
- Approved
- Assignee:
- Mattias Backman
- Definition:
- New
- Series goal:
- Accepted for trunk
- Implementation:
-
Implemented
- Milestone target:
-
2012.01
- Started by
- Mattias Backman
- Completed by
- Mattias Backman
Related branches
Related bugs
Sprints
Whiteboard
[mabac, Jan 12, 2012]: Broken out the lane freezing to https:/
[asac, Jan 12, 2012]: Depending on amount of work I would suggest to schedule this for january (very easy) or february (everything else)
[dzin, Jan 20, 2012]: please report progress and add work items for this blueprint
Meta:
Headline: status.linaro.org lane views show a high level progress indicator for a quarter with blueprints delivered vs. planned
Acceptance: quarterly lane view has a progress bar at the top of the page showing blueprints delivered vs. planned rolled up from all cards.
Work Items
Work items:
Add the progress bar: DONE