Design database model for sprint 2. Please note that this is by no means final database, only as much of it as is required to implement the features that will be implemented in sprint 2. 0,5 ohtudays.
Blueprint information
- Status:
- Complete
- Approver:
- None
- Priority:
- Undefined
- Drafter:
- Tarkisto Developers
- Direction:
- Needs approval
- Assignee:
- Tarkisto Developers
- Definition:
- Drafting
- Series goal:
- Accepted for tenttiarkisto
- Implementation:
- Implemented
- Milestone target:
- sprint-2
- Started by
- Sami Saada
- Completed by
- Sami Saada
Whiteboard
(?)
Work Items
Dependency tree