Lucid Ubuntu Developer Week
Registered by
Jono Bacon
The Lucid Ubuntu Developer Week.
Blueprint information
- Status:
- Complete
- Approver:
- Jono Bacon
- Priority:
- Low
- Drafter:
- None
- Direction:
- Approved
- Assignee:
- Daniel Holbach
- Definition:
- Approved
- Series goal:
- Accepted for lucid
- Implementation:
- Implemented
- Milestone target:
- ubuntu-10.04
- Started by
- Daniel Holbach
- Completed by
- Daniel Holbach
Related branches
Related bugs
Sprints
Whiteboard
Deadlines:
Planning Begins - 16th Dec
Schedule Ready - 15th Jan
Promotional Planning IRC Meeting - 18th Jan - 6pm UTC in #ubuntu-meeting
Ubuntu Developer Week - 25th - 29th Jan
Work items:
[dholbach] Issue a call for sessions: DONE
[dholbach] Finalize schedule: DONE
[dholbach] Schedule promotional campaign: DONE
[jonobacon] Finalize changes to Lernid: DONE
(?)